Distributed energy for shared buildings · fictional developer

Make the building behave like an energy system.

Sunroom designs solar, batteries, controls and essential-load circuits around the way a site actually uses power. The point is not more equipment. It is a clearer relationship between generation, demand, resilience and cost.

Site SRG-18 / 14:20

38.6 kW

roof generation

72%

battery state

21.4 kW

building demand

-6.8 kW

grid import

Residential roof with solar panels

About / system view

Panels make electricity. A microgrid decides what the site should do with it.

Sunroom is a fictional distributed-energy practice for apartment buildings, schools, workshops and small campuses. We start with interval demand, outage priorities and the site's electrical topology before selecting hardware.

The design then coordinates generation, storage, essential loads and grid interaction around an operating objective: reduce peak import, improve resilience, share generation fairly or combine those goals without hiding the trade-offs.

Offerings / system layers

01

Site study

Interval load analysis, roof and plant review, essential-load map, tariff model and electrical constraints.

02

Solar design

Array layout, yield assumptions, inverter architecture and maintainable access around the roof.

03

Storage

Battery sizing against actual load shapes, outage objectives, cycle strategy and replacement assumptions.

04

Controls & commissioning

Metering, operating logic, protection, alarms, handover tests and a measured commissioning report.

Process / from meter to operating rule

Design the decision logic before the equipment list.

1

Observe

Collect interval demand, bills, outage history and site constraints.

2

Prioritise

Separate essential, flexible and discretionary loads; agree what must remain live.

3

Model

Test solar, storage and control scenarios against tariff and resilience objectives.

4

Engineer

Resolve protection, metering, cable routes, roof loads and equipment interfaces.

5

Commission

Prove control logic and islanding where applicable, then compare measured behaviour with the model.

Projects / site stories

Different buildings need different rules.

Solar panels arranged across a green field

SITE 018

Courtyard 36 / apartment block

Common-area solar had been proposed without considering daytime vacancy. The final concept prioritised hot-water load, lift resilience and a smaller battery rather than maximising roof coverage.

SITE 019

Ridgeview School / learning campus

Classroom loads fell before afternoon solar peaked. Storage was modelled around evening sports lighting and essential IT instead of generic self-consumption.

SITE 020

Makers Row / light-industrial cluster

Three tenants had different demand peaks. Shared metering and allocation rules were designed alongside the electrical upgrade so cost-sharing was not left to monthly spreadsheets.

Proof / measured performance

Commissioning ends with evidence, not screenshots.

14

sites modelled this year

31%

median peak import reduction in commissioned examples

100%

essential circuits function-tested

90 d

post-handover performance review

People / system team

Electrical, commercial and operational decisions meet in one model.

Power systems engineer

Thando Maseko

Protection, controls, single-line design

Energy modeller

Ari van Wyk

Interval data, tariffs, storage scenarios

Site delivery lead

Leila Osman

Contractors, commissioning, resident handover

Insights / grid notes

Self-consumption is not the only objective

A battery sized only to absorb midday solar may be wrong for a site whose real priority is carrying essential loads through outages.

Governance is part of electrical design

Shared solar needs agreed allocation, metering ownership and maintenance responsibility before residents can trust the system.

Commission the controls under failure

A normal sunny day proves little. Test loss of grid, low battery, communications failure and safe recovery while the team is still on site.

FAQ / before procurement

Is a microgrid the same as rooftop solar?

Not necessarily. The fictional Sunroom model combines generation, loads, storage, controls and an agreed operating objective. A site can have solar without functioning as a coordinated microgrid.

Can an existing solar installation be included?

Yes. We would first review inverter compatibility, metering, protection settings, warranties and available control interfaces before assuming legacy equipment can participate.

What happens during a grid outage?

Only systems designed and approved for islanded operation can continue energising selected circuits. Essential-load design, protection and safe reconnection are part of the engineering scope.

How do residents know who benefits?

Shared-generation projects need an allocation method before hardware is installed. The fictional process models tariff, common-area load, tenant allocation and governance so the commercial rules are visible.

Contact / site study

Send the bills, the single-line and the outage problem.

We will tell you what data is missing before proposing equipment, then build the first model around actual site behaviour.

study@sunroomgrid.example